I hesitated to pass this information along, but I don’t see any reason not to (the information seems to line up fairly reasonably). A user on the TRX forum posted this:
- The most updated schedule was released on 7/30
- This schedule shows 21MY buildout on 8/31
- This schedule show 22MY job 1 as 9/1 (was previously 8/26 on a schedule released 7/16)
- There aren't any planned periods of downtime aside from Thanksgiving and Christmas.
- Between 9/1 and 12/31, there are 10 planned production Saturdays
- Between 9/1 and 12/31, there are 7 planned production Sundays (they are really trying to get these trucks out)
- Between 9/1 and 9/10, the plant will be in a 'Launch Curve' with daily numbers increasing over that period
- Starting with Saturday, 9/11, the plant will produce at 1,435 JPD (jobs per day for all DT) and continue at that rate, which is considered 'reaching straight time'
- Production is scheduled on Friday, 11/26 (Black Friday)
- Production is scheduled 12/27 through 12/30, which is typically a shutdown period for automotive plants
Obviously, that info is subject to change. And I’m surprised by the daily target of 1,435/day considering they consistently miss their current targets of 1,335/day. Hope springs eternal, I guess.